There are a number of one-time activities and checks that need to take place on migration day. Please add yours here. Please point to the related issues as well.
PIFR/PIFT/Testing
- All existing branch test results should be flushed and requeued, as the existing ones will have all the wrong information.
- qa.drupal.org will have to be updated to the 6.x-3.x branch of project_issue_file_review and configured (and tested). We will need root on that machine to do this. Or is it done in hudson now?
- Existing testbots will have to be updated to 6.x-3.x and configured and tested.
Documentation switch
- Update CVS references and remove old CVS Docs. See items tagged git deployment
Other
*